The project

Sidi Chennane mine

Industry Fertilizers
Customer OCP
Location Khouribga (Morocco)
Year of commissioning 2013

TAIM WESER designed, manufactured and supplied the bulk material handling system for OCP Sidi Chennane’s extraction area, inside Khouribga and Mea production zones.

The projects scope of supply included 3 bucketwheel reclaimer machines with 2.800 tph of capacity and 50 m boom length, the belt conveying system, 8.000 m length, designed in 2 flights, as well as other ancillary equipment.

Sidi Chennane stockyard
Sidi Chennane stockyard
Sidi Chennane stockyard
Sidi Chennane stockyard

The Challenge Achieved

TAIM WESER has been present since early 90’s in several OCP projects for the conveying and handling of phosphate, as the one for Youssoufia washery plant, where TAIM WESER supplied a phosphate conveying system and a waste tailings system, equipped with a stacker and a bucketwheel reclaimer machines. Another project was performed at El Wafi plant, where TAIM WESER supplied an overland conveyor system, designed in 5 flights, with 22 km length and 2.800 tph of capacity, connecting Sidi Chennane and El Wafi stockyards.

The project figures

MaterialPhosphate
Conveying capacity2.800 tph
Boom length50 m
Conveyors length8.000 m

The project gallery

Contact us

On the grounds of legitimate interest, TAIM WESER, S.A. informs you that the personal data that you provide by filling in this form will be processed by TAIM WESER, S.A. as the data controller of this website in compliance with Regulation (EU) 2016/679.

Your data will be stored for the time required to manage and resolve your query. No transfers of you data are envisaged.

You can exercise your rights of access, rectification, opposition, limitation, erasure and portability of data at any time by contacting gdpr@taimweser.com.

Top